The Spokane County Building and Planning Department has received a building permit application for a presumed Amazon.com Inc. distribution center. The application lists the project value at $181 million.
The project site is on the West Plains, on the n
Amazon.com Inc. is on track to begin construction here as soon as early summer on a massive fulfillment center planned near Spokane International Airport, planning records indicate.
Technical and environmental documents recently filed with Spokane County
The city of Spokane recently issued its environmental report card, which highlights an ongoing menu of eco-friendly efforts to support and encourage environmental sustainability through financially stable means, says Catherine Olsen, the city's environmen
A few weeks after expressing optimism that he might turn a profit this year, the promoter of the half-mile oval racetrack at Spokane County Raceway has raised the black flag on the season.
On April 30, Rick Nelson, owner of Spokane Super Oval LLC, anno
Since the launch of the Washington Retirement Marketplace last month, the nation's first state-verified online marketplace for low-cost retirement plans, its director, Carolyn McKinnon, says the program is receiving an encouraging number of calls and we
The Spokane County Planning Department is reviewing conceptual plans for a massive distribution facility to be constructed near Spokane International Airport.
While the name of the company that will operate the facility is conspicuously absent from the p
Efforts to fast-track infrastructure improvements and the construction permitting process in the 800-acre Barker-Euclid industrial area in northeast Spokane Valley have helped attract economic development there.
Menlo Park, Calif.-based design-build cont
Coeur d'Alene-based health network Kootenai Health has started work on the $12 million third phase of construction and expects to complete its $45 million second phase this summer at its main hospital campus, at 2003 Kootenai Health Way, near the northw
Planning and permitting activities are continuing for two long-envisioned commercial centers on the upper South Hill.
QueenB Radio Inc. is planning a center recently renamed Radio Tower Village on 17 acres of land known as the KXLY site on the west side
Greenstone Corp., the Liberty Lake-based real estate development company, has started the permitting process for a $50 million phase of construction in Kendall Yards urban village, on the north bluff of the Spokane River gorge northwest of downtown Spokan